Info View Items

Info View Item Description
Pile ID Unique id of the selected pile
Pile Type The type of the selected pile
Pile Length Length of the current pile
Mast Tilt Front/Back Angle (in degrees) of the front/back tilt of the mast relative to normal
Mast Tilt Left/Right Angle (in degrees) of the left/right tilt of the mast relative to normal
Target Forward/Back Distance to the pile in the front/back direction of the machine
Target Left/Right Distance to the pile in the left/right direction of the machine
Target Distance Distance to the pile
Pile Design Northing Design northing of the selected pile
Pile Design Easting Design easting of the selected pile
Pile Design Elevation Design elevation of the selected pile
Pile As-Built Northing Actual northing of the selected finished pile
Pile As-Built Easting Actual easting of the selected finished pile
Pile As-Built Elevation Actual elevation of the selected finished pile
Pile Delta Northing Difference in northing between the designed and as-built pile
Pile Delta Easting Difference in easting between the designed and as-built pile
Pile Delta Elevation Difference in elevation between the designed and as-built pile
Pile Design Dip Angle Design dip angle of the selected pile
Pile Design Side Angle Design side angle of the selected pile
Pile Design Azimuth Design azimuth (heading) of the selected pile
Pile As-Built Dip Angle Actual dip angle of the selected finished pile
Pile As-Built Side Angle Actual dip angle of the selected finished pile
Pile As-Built Azimuth Actual dip angle of the selected finished pile
Pile Delta Dip Angle Difference in dip angle between the designed and as-built pile
Pile Delta Side Angle Difference in side angle between the designed and as-built pile
Pile Delta Azimuth Difference in azimuth (heading) between the designed and as-built pile
Pile Start Time The time at which the selected pile was started.
Pile Stop Time The time at which the selected pile was stopped.
Total Pile Time Total amount of time spent piling.
Average Pile Time Average time spent piling a single pile.
Current Pile Time Amount of time spent piling the selected pile.
Total Piles Total number of piles...
Piles Driven Number of piles that have been completed
Piles Remaining Number of piles that are not completed
Piles Driven Today Number of piles that were "completed" today