Pile Refusal Settings

These settings allow piles to be marked as refused for reporting in Carlson Command. Refusals can be flagged one of three ways:

  1. Time Only: If a pile takes longer than the Time settings to be driven, it is marked as refused.
    Time
    Time Only
  2. Time and Distance: This setting is a rate of pile driving.
    Time and Distance
    Time and Distance

    For example, if the PD25 is failing to drive the pile at a rate of one foot (or .3m) per 30 seconds at the end of the piling, the pile will be flagged as refused.

  3. Both: Both sets of settings are applied and if either condition is met the pile is flagged as refused.
    Both
    Both